SWIP Power Line Zoning Permit Appeal

By Jeff A. Pierson · September 21, 2025

Public Hearing – SWIP Power Line Appeal
Monday, September 22, 2025 - 6:00 PM
Jerome County Courthouse
Jack Nelson Room (Room 306)

The appeal of the Jerome County Planning & Zoning Commission’s approval of the SWIP power line is being led by Dean Dimond and Julie DeWolfe Arroyo, residents directly affected by the project. According to Dean, their primary concern is that the county failed to follow its own ordinances when granting the special use permit for the massive transmission towers.

What is SWIP?
The Southwest Intertie Project (SWIP) is a long-planned 500-kilovolt transmission line intended to connect Idaho’s Midpoint substation to Nevada and on into California, forming a north–south electricity corridor across the West. First conceived in the late 1980s, it has been promoted by federal agencies and utilities as a way to strengthen grid reliability and enable bi-directional energy flow. Supporters argue it offers regional stability and new transmission capacity, but critics in Idaho see it as an export highway designed mainly to send low-cost Idaho power to California. To opponents, SWIP represents not a benefit to Idaho but an imposition of California’s unstable energy policies and higher risks onto Idaho families and businesses.

Beyond the procedural flaws, they have argued that the Southwest Intertie Project (SWIP-North) does little to benefit Idaho. With up to 80 percent of the line’s capacity already contracted for out-of-state use, the project functions more as an export corridor for California than a resource for Idaho communities.

For Dimond, Arroyo, and many others, the appeal is not simply about transmission towers. It is about whether Jerome County residents will have a meaningful voice in decisions that reshape Idaho’s energy future

Sources